Project: Temporary, Unique output, Closed after goal is met (e.g., Constructing Metro line).
Operation: Ongoing, Repetitive, Sustains business (e.g., Running daily Metro trains).
| Role | Primary Responsibility |
|---|---|
| Project Manager | Overall planning, execution, and closure; responsible for deliverables |
| Project Sponsor | Provides financial resources, business case & project charter |
| Consultant | Offers specialized technical/advisory expertise on specific tasks |
Level 1: Total Project → Level 2: Major Deliverables → Lowest Level: Work Package.
DCET Trap: WBS does NOT show activity sequence or time dependencies — that's done by Network Diagrams!
Avoid: Change plan to eliminate threat entirely.
Mitigate (Reduce): Take actions to lower probability/impact (e.g., Backup generator).
Transfer: Shift financial impact to 3rd party (e.g., Insurance / Warranty).
Accept: Acknowledge risk when cost of mitigation exceeds potential impact.
Monitoring: Continuous, day-to-day tracking of inputs, activities & outputs.
Evaluation: Periodic assessment of overall relevance, effectiveness, and impact.
| Feature | CPM (Critical Path Method) | PERT (Program Evaluation & Review Technique) |
|---|---|---|
| Nature of Time | Deterministic (Known with certainty) | Probabilistic (Uncertain / Estimated with probability) |
| Time Estimates | Single Time Estimate per activity | Three Time Estimates: Optimistic (to), Most Likely (tm), Pessimistic (tp) |
| Orientation | Activity-Oriented | Event-Oriented |
| Typical Application | Construction, Civil works, Repetitive projects | R&D, Space missions, Defense, New drug development |
| Cost Focus | High focus on Time-Cost tradeoff (Crashing) | Primarily focused on Time estimation & control |